24.8 C
Kuala Lumpur
Tuesday, February 3, 2026
HomeNewsPIA expansion reaches 38% completion, phase one on track

PIA expansion reaches 38% completion, phase one on track

Date:

Related stories

Government mulls housing above railway stations to curb congestion

The federal government is studying a proposal to build...

State to prioritise traffic management amid Penang’s infrastructure boom

The Penang state government will implement comprehensive traffic management...

Merione Grand | Penang Property Talk

Merione Grand Merione Grand is an upcoming business hub by...

3 major projects underway at Penang General Hospital to boost public healthcare

Three major development projects currently underway at Penang General...

PROPOSED: Residential development in Balik Pulau (Affordable terrace, terrace, and semi-d)

PROPOSED: Residential development in Balik Pulau (Affordable terrace, terrace,...

PIA expansion reaches 38% completion, phase one on track

pia-expansion-model

The Penang International Airport (PIA) expansion project is progressing steadily, with Phase One expected to be completed by the end of this year. As of now, construction work has reached nearly 38% completion.

State Infrastructure, Transport and Digital Committee chairman Zairil Khir Johari announced that Work Package 1 (WP1) has surpassed the 37% mark. WP1 covers critical enabling and upgrading works, including the construction of an ancillary building, a new air traffic control tower, the Civil Aviation Authority of Malaysia (CAAM) office, an aviation security tower, substations, and other supporting infrastructure.

Zairil also revealed that physical construction under Work Package 2 (WP2) commenced last month. This package focuses on upgrading the airport’s apron, taxiways, airside drainage, utilities diversion, and related infrastructure. WP2 was awarded to Acre Works Sdn Bhd in December 2024, with a contract value of RM254.6 million.

Looking ahead, the tender for Work Package 3 (WP3)—which involves expanding the new passenger terminal building—will be called in June. The new terminal is scheduled to begin operations in 2027, with full project completion targeted for 2028.

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from up to 5 devices at once

Latest stories

LEAVE A REPLY

Please enter your comment!
Please enter your name here